Winds of Change for K.C. Electric Association
Three proposed wind farms are being developed in K.C. Electric’s service territory on Colorado’s eastern plains. The Cheyenne Ridge wind farm is a 500-megawatt wind farm developed by TradeWind Energy. NextEra Energy will develop a 300-megawatt wind farm south of Flagler called Bronco Plains. And EDP Renewables is developing a 104-megawatt wind farm south of Seibert called Crossing Trails.
The Crossing Trails project is located in both Kit Carson and Cheyenne counties and will require a new 230,000-volt transmission line to be built from the wind farm to an existing transmission line. K.C. Electric’s power provider, Tri-State Generation and Transmission, has signed a power purchase agreement with EDP to purchase the output of the Crossing Trails wind farm, some of which will be distributed into K.C.’s system. It is expected that these three wind farms will be in service by the end of 2020.